Development progress
Where the development stands today
The scheme design is complete and the project is working through environmental and planning approvals. Construction has not started, and no completion date is published until the programme is confirmed after contractor selection.
- Current stage
- Design and approvals stage
- Stages complete
- 1 of 5
- Units planned
- 30
- Construction
- Not started
- Completion date
- On confirmation
- Status reviewed
- 24 September 2026
Implementation sequence
From scheme design to handover
The programme below is the project implementation sequence. Only stages that are actually signed off are marked as completed.
- Completed
- In progress
- Planned
- 01
Scheme design
CompletedSite appraisal, unit mix, architectural layouts and the design approach that fixes what is being built at Michamvi.
- Site appraisal and development brief
- Unit mix: 10 two-bedroom and 20 three-bedroom apartments
- Architectural layout drawings: site plan, apartment types and common facilities
- Structural, roofing and finishes approach
- Order-of-magnitude cost planning
- 02
Environmental and planning approvals
In progressStatutory submissions to the relevant Zanzibar authorities so the scheme can be permitted as designed.
- Environmental submission and review
- Planning approval of the scheme
- Coordination with the relevant authorities and utility providers
- 03
Detailed design and tender
PlannedThe approved scheme is developed into construction documentation and priced by contractors.
- Detailed architectural, structural and services drawings
- Specifications and schedules
- Bills of quantities
- Tender issue and contractor pricing
- 04
Building permit and contractor selection
PlannedPermit in place and a contractor appointed against a confirmed construction programme.
- Building permit issued
- Contractor appointment and contract signing
- Confirmed construction programme and site set-up
- 05
Construction and defects liability period
PlannedDelivery of the 30 apartments, shared facilities and site infrastructure, followed by the defects liability period.
- Substructure, superstructure and roofing
- Finishes, services and joinery
- Pool, gym, wellness suite and convenience store fit-out
- Landscaping, parking and site infrastructure
- Practical completion, handover and defects liability period
What this means for buyers
Buying before completion
Buying during the design and approvals stage is normal for a development of this kind, but it changes what you should check before paying a deposit.
Read carefully
This information is provided for general marketing purposes only and does not constitute an offer, contract or warranty. Architectural drawings, renders, dimensions, finishes and amenities are indicative and subject to change during detailed design, statutory approvals and construction. Unit availability and selling prices are confirmed in writing by Mohafrin.Ask us for
- Latest approvals position
- On request
- Confirmed construction programme
- After contractor selectionPublished once the programme is fixed
- Payment structure and milestones
- On enquiry
- Unit availability schedule
- On enquiry
- Unit-level specification
- On reservation
Anything that affects a purchase decision is confirmed in writing before you commit. Ask us for the current position rather than relying on an older copy of this page or of the brochure.
Kept up to date
Michamvi Apartments
As each stage is completed we update this page, and the status above is dated so you can see how current it is. For anything that affects a purchase decision, ask us for the confirmed position in writing.
Michamvi Apartments Development Brochure
The Mohafrin brochure for the Michamvi Apartments Development, issued as a printable PDF.
- Format
- PDF, 28 pages
- File size
- 6.0 MB
- Edition
- 24 September 2026
mohafrin-michamvi-apartments-brochure.pdf
Prices, unit availability and the confirmed construction programme change during the sales period, so ask us for the latest written confirmation rather than relying on any document alone.